Blockchain dYdX halt during the network upgrade to v5.2.0 on Aug 6, 2024
Scheduled Maintenance Report for Fireblocks
Completed
The scheduled maintenance has been completed.
Posted Aug 06, 2024 - 18:35 UTC
Verifying
Verification is currently underway for the maintenance items.
Posted Aug 06, 2024 - 18:27 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 06, 2024 - 17:50 UTC
Scheduled
The dYdX Mainnet will perform an upgrade on Aug 6 at around 17:50 UTC.

The upgrade will take place at Target Block: #22,170,000. The upgrade will be completed once the network’s nodes finish upgrading. A short while before that time, Fireblocks will halt all activities on the dYdX blockchain, as the network may be disrupted during the upgrade, which is expected to last around 1 hour. Once the upgrade is completed, Fireblocks will re-enable the activity.

You can find more information about the upgrade here:
https://dydx.forum/t/drc-dydx-chain-protocol-v5-2-0-software-upgrade/2889
Posted Aug 02, 2024 - 23:06 UTC
This scheduled maintenance affected: Blockchain nodes (DYDX).